A supplier slips from Tuesday to Friday. Which production orders need to move?

Follow a 20-part shortage from a purchase order to a customer commitment, then test whether a split delivery can keep production on schedule.

17 Nov 20265 minMicrosoft Learn
ERPProcurementProduction PlanningMicrosoft Dynamics 365
A production planner examines a metal bracket beside a schedule on the factory floor
AI-generated editorial illustration

Purchasing expects 100 mounting brackets on Tuesday, but the supplier says they will arrive Friday. Thursday morning’s assembly run needs 80. The warehouse has 40 ready to use, with another 20 due Wednesday. That leaves a shortage of 20. Purchasing now has a specific request to take back to the supplier. Can at least 20 brackets arrive in time for production to pick them?

This hypothetical example is for plants deciding whether to expedite parts, resequence production, or warn a customer about a possible delay. It assumes all 60 brackets are available to pick from the right warehouse and none are reserved for other work. It also leaves minimum stock out of the arithmetic.

Follow the shortage to the orders waiting for parts

Start with demand for the same component. Check when each job needs it, when the warehouse can actually release it, and which jobs already have reservations. If the 20 brackets arriving Wednesday stay in receiving inspection until Thursday afternoon, the morning assembly run has only 40 available. A partial shipment of 20 would still leave a shortage.

Then open the production order waiting for those components and follow it to the sales orders it supplies. A customer order with finished goods already allocated may still ship on schedule. For orders that depend on the run and have little schedule slack, Sales and Planning should assess the delivery date together. Before contacting the customer, check whether there is enough time for quality checks and shipping after assembly.

What Dynamics 365 uses to assess the impact

In its September 23, 2026 update, Microsoft said that Procurement Agent impact analysis in Dynamics 365 Supply Chain Management was in public preview. As of our November 17, 2026 check, the Microsoft Learn overview, last updated August 10, 2026, still describes it as a production-ready preview. The overview also says the analysis incurs charges based on the number of Microsoft Copilot Studio credits used. Check the terms and costs before planning a trial. Microsoft product update · Overview and charges

The feature uses available links between supply and demand. Those can include explicit links between orders and links calculated by the latest plan, known as pegging. It checks them against projected inventory to assess effects on production orders, sales orders, transfers, and stock levels. Microsoft documents analysis for later delivery dates, reduced quantities, and canceled lines. If the plan is stale or downstream links are missing, have a planner verify the affected orders before accepting the supplier’s proposal, even when the system reports no impact. How Dynamics 365 calculates impact

Test the tool with one purchase order

Have Purchasing and Planning agree on the expected results before a sandbox demo. First, move all 100 parts to Friday. The tool should show Thursday morning’s shortage of 20 and identify the affected production order. For the second scenario, set 20 parts to arrive in time to pick and the remaining 80 on Friday. Check whether that covers the run. If the plant has a minimum stock level, check the remaining balance after the run. A balance below the threshold can put later jobs at risk even when this one has enough parts.

In Dynamics 365, the simulation lets you test changes to dates or quantities on existing lines. It uses the planning data available at the time and leaves the actual purchase order untouched. Microsoft’s simulation guide

Ask the presenter to open the incoming receipts, reservations, and production orders behind the result so the team can check the numbers. Once they know which production order is short of parts, Purchasing can negotiate a specific quantity, Planning can decide whether to move the run, and Sales can see which customer to call first.